Your single point of reference for all your Geotechnical Inquiries

Publications by [Moll S.]

Total Items found:
The 182 m high concrete face rockfill dam (CFRD) is one of the main components of the Nam Ngum 2 (NN2) hydropower scheme in Lao PDR. Construction of the dam was essentially completed in March 2010 and reservoir impounding commenced subsequently. This paper ...
Reference: 6TH INTERNATIONAL CONFERENCE ON DAM ENGINEERING, C.Pina, E.Portela, J.Gomes (ed.), Lisbon, Portugal, February 15-17, 2011
Nam Ngum 2 dam, a large concrete face rockfill dam (CFRD) of 182 m height, is under construction and impounding is scheduled to start at beginning of April 2010. The dam is situated in a narrow valley and founded on sedimentary rock of variable strength. Dam ...
Reference: The 1st International Symposium on Rockfill Dams, Chengdu, China 2009