FLOWSHEET DEVELOPMENT FOR THE SUKARI GOLD PROJECT IN EGYPT (2009)

The Sukari project, which is owned by Centamin Egypt Ltd, is located in southern Egypt, 770 km south of Cairo but close to the Red Sea. The project is the first new gold development in Egypt and was commissioned in the middle of 2009.
In 2007, Centamin purchased the CIL plant from the Kori Kollo mine in Bolivia. This plant was originally designed to treat 6.5 Mtpa of oxide ore.
The project lies in one of the driest deserts in the world and a feature of the operation is the use of sea water from the Red Sea. This water is pumped 25 km from the coast.

Reference:
World Gold Conference 2009, The Southern African Institute of Mining and Metallurgy, 2009
Organization:
Bateman Engineering Pty Ltd, Western Australia
Australia
User Rating: