This is a paper that discusses, in a practical/empirical manner, the movements - and their impact on the support measures- which have been measured during the excavation of the top heading of the Driskos motorway tunnel (now in operation), during the years 2000 to 2002. The total length of the tunnel is almost 4.5km and consists of two parallel 12m span tunnels. It belongs to the Egnatia Motorway in Northern Greece. The measurements of 37 (3-point) monitoring stations have been analyzed and evaluated.
Reference:
ITA - AITES World Tunnel Congress 2009
ITA - AITES World Tunnel Congress 2009
Organization:
Egnatia Odos A.E., Greece
Greece
Egnatia Odos A.E., Greece
Greece