The QuickShot system combines pre-programmed electronic detonators with special on-bench components that enable the user to quickly and easily design the firing sequence solely by using the order of connections. This precludes the user from having to deal in absolute delay times. The connecting system enables benches to be hooked-up speedily by multiple users who have differing levels of experience. This paper provides details of how, after 33 months, the system has been embraced by the project by aiding in maximised advances, improved cycle times and meeting the  required environmental constraints.